SUBJECT: A) Approval to post the Notice of Intent and Award Bid No. 21/22-54, CR 220 At Town Center Blvd. Intersection Improvement Project (RE-BID) to Hubbard Construction Company in the amount of $846,030.39. Approval will be effective after the 72 hour protest period has expired.
B) Additional approval of the accompanying agreement with Hubbard Construction Company. The Contractor shall accomplish material acquisition within 180 calendar days from the NTP Date. Construction days will start as soon as Contractor begins work in the area, and shall have 60 days to complete construction.
Funding Source:
Capital Improvement Plan (CIP) Projects Fund – Non Capital Improvement Element – Intersection Improvements Minor Capacity - Infrastructure
Capital Improvement Plan (CIP) Projects Fund – All Grants Organization – Town Center Blvd Intersection - Infrastructure