Clay County Board of County Commissioners | Clay County Administration Building Tuesday, April 11 4:00 PM |
|
| | | | | | | | TO: Board of County Commissioners
| DATE: | | | FROM: Administrative and Contractual Services | | | | SUBJECT: Approval of the Ninth Amendment to Agreement No. 2020/2021-213 with Jacobs Engineering Group Inc. for Professional Engineering Design Consultant Services for the Bonded Transportation Program Construction Management At Risk Group #2 regarding Project 5 in the total amount of $89,947.40. This approval is contingent upon closing on associated stormwater pond property.
Funding Source:
2020 Bond Construction Fund - CR220 Baxley to Henley - Infrastructure
| | | AGENDA ITEM TYPE: | |
| | | | | |
| | | | | | | | BACKGROUND INFORMATION: | Amends the scope of services to include the redesign of Pond 1C to the property location referred to as the Bunker property for Project 5 to include revisions to the roadway and drainage plan sheets for approximately 1,000 feet to modify the pond location and design, as well as the storm water collection system and pond outfall system in the total amount of $89,947.40. |
| | | | | |
| | | | | | | | Is Funding Required (Yes/No): Yes | If Yes, Was the item budgeted (Yes\No\N/A): Yes |
Funding Source:
2020 Bond Construction Fund - CR220 Baxley to Henley - Infrastructure
Account No.:
FD3010 - CC1231 - PRJ100201 - SC563000
Sole Source (Yes\No): No | Advanced Payment (Yes\No): No |
| | | | | |
| | | | | | | | Planning Requirements:
Public Hearing Required (Yes\No): No
Hearing Type:
Initiated By:
Not Applicable | | | | | |
REVIEWERS: | Department | Reviewer | Action | Date | Comments | Administrative and Contractural Services | Thomas, Karen | Approved | 4/5/2023 - 4:07 PM | AnswerNotes | County Manager | Wanamaker, Howard | Approved | 4/5/2023 - 4:18 PM | AnswerNotes |
|
|