The County requested bids from qualified Contractors to perform the widening County Road 220 from existing 2-lane rural roadway to a 4-lane urban roadway from east of Henley Road to west of Knight Boxx Road including bridge work. Substantial Completion shall be accomplished within 525 days from Notice to Proceed and Final Completion shall be accomplished within 570 days from Notice to Procced.
844 Suppliers were notified
46 Suppliers downloaded the Bid
4 Bids were received
1 No Bid was received
6 Contractors attended the Mandatory Pre-Bid meeting
Pursuant to Chapter 5, Section C of the Purchasing Policy, the County Manager is authorized to approve and execute the agreement on behalf of the Board following Board approval of the award.