SUBJECT: Approval to accept Staff's ranking and selection of the top ranked Consultant for RFQ No. 23/24-080, Clay County Judicial Facility Master Plan. Approval of award will be effective after the 72 hour protest period has expired.
1. Dewberry Architects, Inc. - 91.7
2. HDR Architecture, Inc. - 88.1
3. Nelco Architecture, Inc, - 76.1
4. Matthews DCCM - 56.8
A committee consisting of Circuit Judge, 4th Judicial Circuit Judge, Clerk of Court and Comptroller, Trial Court Administrator, Director of the Clay County State Attorney's Office, and Facilities Operation and Maintenance Division Director performed the evaluation and ranking of the responses received. If desired, the Board may request presentation from a minimum of the top three ranked Consultants. An Agreement will be negotiated and brought back to the Board for approval.
Funding Source:
Court Facilities Fund - Court Facility - Professional Services